NEW CAASA Q&A
Question:
I am acting as an adjudicator and one of the parties is challenging my jurisdiction. I know I need to enquire into my jurisdiction. What do I need to consider?
Answer:
Some of the questions you should be asking are:
- Is there an agreement to refer disputes to adjudication?
- Has the adjudicator been properly appointed in terms of such agreement?
- Has a dispute arisen which is capable of being referred to adjudication?
- Are the parties to the dispute the same as those that entered into the contract?
- Has the dispute been previously decided?
Regardless of whether there is a challenge to the adjudicator’s jurisdiction, there should always be an enquiry into jurisdiction
Where a challenge has been made the adjudicator should investigate such challenge and satisfy themselves as to the validity or otherwise of such challenge. If the challenge has merit then the adjudicator should refuse to proceed with the adjudication unless and until he or she has jurisdiction. If the challenge is without merit, then the adjudicator should notify the disputing parties of his or her view and proceed with the adjudication.
Have an adjudication related question that you would like answered? Email us at admin@adjudicators.co.za.
|
|
|
CAASA ANNUAL GENERAL CONFERENCE 2020
Save the date for the 2020 CAASA Annual General Conference.
Members and non-members are asked to save the date for the upcoming webinar conference on the 19th November 2020, where industry experts will discuss pertinent aspects of Adjudication as a dispute resolution method in the construction industry.
|
|
|
CAASA PANEL MEMBER HIGHLIGHT
This month we feature CAASA panel member, Brad Boertje, and ask him to outline one of his most recent adjudications.
I have recently acted as adjudicator in a very interesting case concerning compensation for escalation. The parties concluded a contract providing for escalation to be reimbursed on a “proven cost basis”. This is a model that it is often used for materials subject to international market prices, such as bitumen and fuel.
However, in this instance, the material concerned was reinforcing steel.
When concluding a contract, the parties attempted to capture their intentions regarding compensation for escalation. Unfortunately, the way the intentions were captured led to a difference of opinion in interpreting the contract, which the adjudicator was called on to resolve.
The crux of the matter concerned what “proven-cost” actually means. The respective parties pled their cases well and the adjudicator was essentially called on to decide if physical proof of actual cost incurred was required to secure compensation for escalation, or if published raw material list prices could be used. I won’t divulge the outcome of my determination as the matter is private and the losing party has proceeded the dispute to Arbitration.
The lesson to be learnt is that an adjudicator cannot make a contract for the parties. When parties are agreeing principles for compensation for escalation, they need to precisely capture what is required to substantiate such claims; alternative methods cannot subsequently be introduced without mutual consent.
To view Brad's profile, click here.
|
|
|
INTRODUCING THE CAASA EXCO
We are pleased to introduce the new CAASA Executive Committee as follows:
Chairman
Norman Milne
chairman@adjudicators.co.za
Deputy Chairman
Francois Spies
Treasurer
Barry Herholdt
treasurer@adjudicators.co.za
Secretary
Kelly Stannard
secretary@adjudicators.co.za
General members
Arvitha Singh
Michelle Kerr
Damian James
Jonathan Ely
Stephanie McDonald
David Spooner
Reg Reynolds
Vaughan Hattingh
|
|
|
|
|
|